Telefónica
Success story at Data Center
Address: Ixtlahuaca, México
Period: September – December 2011
REENGINEERING AND INSTALLATION OF TELECOMMUNICATIONS INFRASTRUCTURE.
INSTALLATION OF NETWORK CABLING FOR THE IMPLEMENTATION OF THE VIDEO SURVEILLANCE SYSTEM.
DESIGN AND IMPLEMENTATION OF THE DATA CENTER.
IMPLEMENTATION OF THE GENERAL MONITORING AND MAINTENANCE SYSTEM.
WHAT WERE THE CHALLENGES?
- Crossing engineering with other disciplines.
- Many people work at the same time in the same area.
- Expectation of UpTime Certification.
HOW DID WE SOLVE THEM?
- Daily meetings were established with the other integrators and the supervisor.
- Coordination so that no more than 2 integrators are working in the same area.
- The recommendations made by our ATD were respected, always seeking to fulfill what is required by UpTime institute.
WHAT HELPED TO BE A SUCCESSFUL PROJECT?
- That the project was a greenfield.
- That the customer was clear about the goal of turning their Data Center into a TIER III
Category: Data Center